Health puts out to tender the construction of the new pediatric tower of the Maternal and Child Hospital



The Ministry of Health of the Government of the Canary Islands has put out to tender by open procedure and ordinary processing the construction project of the new pediatric tower Canary Islands Maternal and Child University Hospital, once the writing of the supervision report for this action has been completed.

After approval of the file, the tender for the work has already been published on the Public Sector Procurement Platform. The budget for this construction will be 43,176,658.02 euros, excluding IGIC, financed with European funds from React-Euy MRR.

The new building will house the neonatology units, comprehensive care for oncology and hematology, infant, pediatric and surgical hospitalization floors, a short-term infant-adolescent hospitalization unit, rehabilitation and a breast unit, among other services.

The deadline for submitting proposals ends on January 27, 2022 and it is estimated that, if the procedure follows the established deadlines, the award of the work could occur during the first half of 2022.

As published in the announcement of this tender, the opening of the envelope with the economic offer will take place on February 1.

You can consult all the information about the tender for this construction on the web portal www.contrataciondelestado.es

Complex work

The construction of this new tower of the Maternal and Child University Hospital, which includes two floors below ground and seven high, requires different phases, since current buildings have to be demolished, which will mean relocating the services that until now are provided in these facilities ( laundry, linen, maintenance and warehouses) in other dependencies of the Hospital Complex.

These demolition works will take place over a period of approximately six months, so they could be completed in 2022.

The new Pediatrics tower will be connected to the two hospital buildings already in operation (the Torre del Mar and the original Maternal building), which has meant drawing up an exhaustive project to guarantee the correct physical and technical connection of the facilities, floor to floor. plant.

The second phase of the project, that of the construction of the tower, has an approximate execution period of 16 months, after which the urbanization and the connection between buildings will proceed.

It is estimated that this entire project can be developed in a period of 36 months.

.